7,2 MWp RUFFORD, UK

Storage

PROJECT SUMMARY

The Alpha Project consists of three  different sites (Lockleaze, Littlebrook, Rufford), and is intended to operate under certain conditions in order to respond to network’s frequency fluctuations (FFR) as well as to participate in Triad avoidance Capacity Market (CM) dispatch (future service).

The import/export capacities of Rufford site are 7.2MW export / 7.4MW import.

Rufford consists of:

Electrical Equipment System:

  • Four (4) inverters 2200kVA nominal power each
  • Four (4) production Transformers 2200kVA nominal power each
  • Four (4) load banks 2000 kW nominal power each
  • Eight (8) diesel engines of 515kW nominal power each

BESS- Battery Energy Storage System:

  • 4 Li-ion Battery Banks of 0.867MWp each, with total energy capacity of 3,138.74kWh
  • EMS- Energy Management System

A “turn-key” control system solution is designed for the purposes of providing frequency regulation, grid balancing and capacity-on-demand services in accordance with the terms of the Contract and any other services that the National Grid may put out to tender in the UK.

UNITED KINGDOM

7,2 MWP

WHERE

53.07’25.5°N
1.06’55.4°W